King Crown Infinity Construction Progress update in December 2024 – Maintaining steady progress, the project fully completed the third-floor structural works in December 2024 and is actively pouring concrete for the fourth-floor slab, column walls, and transfer slab formwork.

Share

In November, King Crown Infinity project completed the third-floor structural works and is now actively pouring concrete for the fourth-floor slab, column walls, and transfer slab formwork. The construction site is bustling with activity day and night, aiming to complete the structural works of the commercial podium before the upcoming Lunar New Year.

With vibrant activity around the clock, the construction team is working towards the completion of the six-story premium commercial podium. The next phase will involve building the superstructure, targeting the handover of the entire project by Q2 2026.

Tien Do King Crown Infinity Thang 12 Nam 2024

King Crown Infinity – Project update December 2024

King Crown Infinity Construction Progress – December 2024 (2)
King Crown Infinity Construction Progress – December 2024 (3)
King Crown Infinity Construction Progress – December 2024 (4)
King Crown Infinity Construction Progress – December 2024 (5)
King Crown Infinity Construction Progress – December 2024 (6)
King Crown Infinity Construction Progress – December 2024 (7)
King Crown Infinity Construction Progress – December 2024 (8)
King Crown Infinity Construction Progress – December 2024 (9)
King Crown Infinity Construction Progress – December 2024 (10)
King Crown Infinity Construction Progress – December 2024 (11)

Thank you for taking the time to learn more about the King Crown Infinity project!

5/5 - (1 vote)

Related posts

King Crown Thu Duc Completes the Structural Work for the Commercial Podium and Transfer Slab

The “Completion of the Structural Work for the Commercial Podium and Transfer Slab” event for King Crown Thu Duc took place successfully on the morning of February 18, 2025, witnessed by esteemed contractors, banking partners, and sales agencies.

Read more →

King Crown Infinity progress latest update on January 2025

King Crown Infinity’s latest progress update – The current status and actual construction progress project site in January 2025

Read more →

Over 2,500 attendees gather at Eaton Park development’s art exhibition

A recent art exhibition of Eaton Park hosted by Gamuda Land in Ho Chi Minh City attracted over 2,500 visitors, showcasing growing interest surrounding the project.

Read more →

Masterise Homes officially launched its first high-rise project Masteri Grand View at The Global City

Masteri Grand View – the first high-rise masterpiece in the new center of The Global City has officially launched, inheriting all the values ​​from the completed infrastructure and complete international standard utility system of this iconic urban area.

Read more →

Leave a Reply

Whatsapp Viber Chat Zalo Zalo Chat (+84) 902 247 239